Accelerators Research (AR), 1961 - 1966

In 1956 on the recommendation of the Director-General, C. J. Bakker, the Scientific Policy Committee endorsed the proposal to set up the Accelerators Research group, which was approved by the Council at its sixth session.

In 1957 the Accelerators Research group was created, as part of the Proton Synchrotron (PS) division to undertake research
on the design of future colliders. In November 1959 the PS started with operation.

In 1960 several members of other groups of PS division joined the PS-AR group. Its mandate was enlarged to include more general studies of as accelerators and related instrumentation technologies.

In 1961 the AR Group became the AR division. Some specific studies were started for possible future CERN accelerators as 

Intersecting Storage Rings (ISR) approved in 1965
Super Proton Synchrotron (SPS) approved in 1971

On January 1967 the AR division was transferred to the ISR Construction Department.

Division Leaders A. Schoch (1961)
K. Johnsen (1962)
C. Zilverschoon (1963)
A. Schoch (1964 - 1966)
AR Divisional Reports
by year
1961 1962 1963 1964 1965 1966   ALL
AR Groups BSt GS PSep SR/SRM SG      
AR Divisional Reports
by group
Groups Leaders Years
AR-BSt Beam Stacking Model   1961
AR-GS General Studies E. Regenstreif (1961)
L. Resegotti (1962)
F. Schneider (1963-1965)
1961 to 1966
AR-PSep  RF Particle Separator Project H. Hereward (1961)
B. Montague (1962-1965
1961 to 1965
AR-SR/SRM Storage Ring Project / Model K. Johnsen (1961)
M. Pentz (1962-1965)
1961 to 1965
AR-SG

Study Group

   - Theory and Parameters
   - Magnet
   - RF and Beam Observation
   - Beam Transfer
   - Vacuum
   - Survey
   - General Engineering Drawing Office (1962-1964)
   - General Layout (1965-1966)
   - General Engineering (1965-1966)
   - Booster Magnet
   - Linac
   - Mechanical Workshop and Stores

K. Johnsen

E. Keil
L. Resegotti
W. Schnell
B. de Raad
E. Fischer
J. Gervaise
F. Bonaudi
F. Bonaudi
H. Horisberger
W. Hardt
P. Lapostolle
B. Räber

1962 to 1965

 

Intersecting Storage Rings (ISR), 1966 - 1982

In 1963 a Working Party of ECFA (European Committee for Future Accelerators) recommended the construction of both
the ISR and the 300 GeV Proton Synchrotron (SPS).

An electron model was built at CERN to verify some of the basic features of the idea of ISR. This model called CESAR came into operation in 1963. 

In December 1965 the CERN Council approved the ISR project and the continuation of the 300 GeV project study (SPS).

In 1966 the ISR division was created and Kjell Johnsen appointed as Division leader.

In 1971 the ISR machine came into operation with the PS as injector.

In 1982 the CERN Council approved the proposal to dissolve the ISR division. The next year most ISR staff moved to the new Large Electron Positron Collider Division (LEP).

In 1984 the ISR were closed down to liberate financial and manpower resources for the construction of the LEP.

Division Leaders K. Johnsen (1966 - 1971)
L. Resegotti (1972)
F. Bonaudi (1973)
F. Ferger (1974 - 1982)
ISR Divisional Reports 1966 1967 1968 1969 1970 1971 1972 1973
1974 1975 1976 1977 1978 1979 1980 1981
1982             ALL
ISR Groups AS BOM BT CO DI EN ES GE
GL GS MA MAG LEP LTD OP PO
RF SM SU TH VA WORKSHOP OTHER  
300-GS 300-LI 300-SI 300-GeV        
ISR Internal Notes & Specifications Internal Notes  Specifications : BT - BOM - CO - MA - VAC
ISR Committees Parameter Committee
Steering Committee
Beam Equipment Interaction Committee (BEIC)
Machine Operation Committee (MOC)
Performance Committee (PERC)
Other ISR series ISR Performance Reports ISR Running-in
ISR Divisional Reports by Groups Groups Leaders Years
ISR-AS Study on proton-proton storage rings   1974
ISR-BOM  Beam Optics & Magnet  L Resegotti 1974 to 1982
ISR-BT  Beam Transfer B. de Raad 1966 to 1971
ISR-CO  Controls / Computer G. Schaffer
P. Wolstenholme
1966 to 1982
ISR-DI Office of the Division leader J. Ducrot 1966 to 1982
ISR-EN  Engineering H. Horisberger 1966 to 1982
ISR-ES  Experimental Support K. Potter 1966 to 1982
ISR-GE General Engineering E. Jones
R. Perin (1978-1982)
1966 to 1982
ISR-GL General Layout F. Bonaudi 1966 to 1982
ISR-GS General Studies F. Schneider 1966 to 1982
ISR-LEP LEP Study Group   1978 to 1980
ISR-LTD Long-Term Development   1966 - 1978
ISR-MA Magnet L. Resegotti 1966 to 1982
ISR-MAG Magasin   1966 to 1969
ISR-OP Operation D. Neet 1966 to 1982
ISR-PO Power Supply S. Van der Meer
H. Isch
1966 to 1982
ISR-RF Radio Frequency & Beam Observation W. Schnell 
S. Hansen (1979)
1966 to 1982
ISR-SM Storage Ring Model M. Pentz
E. Jones (1969)
1966 to 1967
ISR-SU Survey J. Gervaise 1966 to 1982
ISR-TH Theory (Since 1970) E. Keil 1970 to 1982
ISR-VA Vacuum E. Fischer (1966-1978)
R. Calder (1979-1980)
H.P. Reinhard (1981-1982)
1966 to 1982
ISR-WORKSHOP Workshop   1977 to 1978
ISR-OTHER Other: Yellow reports, pres release, ...    
ISR-300-GS 300 GeV General Studies (until 1969) W. Hardt 1966 to 1969
ISR-300-LI 300 GeV Injection (until 1969) P. Lapostolle 1966 to 1969
ISR-300-SI 300 GeV Project - SI   1966 to 1967
ISR-300-GeV 300 GeV Project   1967

 